In January 2021 the Ministry of Infrastructure announced nearly $2.0 million in funding for a $5.8 million project being undertaken by Tbaytel to bring high speed fibre to over 1750 addresses in the Municipality.  The target area is broken into 11 Fibre Service Areas (FSA).  Last year Tbaytel completed installing fibre infrastructure, e.g., lines and equipment, in 3 FSAs, and has begun connecting customers.  Future work in the remaining FSAs is currently scheduled as follows:

- Hwy 130: July 2022

- Pole Line Rd: Sept 2022

- Hwy 102 St 2: Dec 2022

- Oliver, Nicholettes, Rosslyn Village and Kakabeka: all planned for 2023 

 

 Below is a link to a Tbaytel website that provides a map with project updates.

 www.tbaytel.net/fibreexpansion